Facts
In anticipation of additional cost-cutting measures, all facts are subject to change. More information
Courtrooms: 26
Square footage: 301,353
Current authorized budget: $277,164,000
Estimated construction costs per square foot are being updated
Current status: Site acquisition; dependent on available funding
Current expected completion: TBD
Historical Documents
Project Feasibility Report
The proposed project would create a full-service courthouse in Modesto to replace seven court facilities - five in Modesto and the two outlying courthouses. Consolidating these facilities will enable the court to increase efficiency by retiring leases and centralizing operations. The project would improve security by providing enhanced entrance screening, separate hallways for the public, staff, and in-custody defendants, and properly sized holding areas for in-custody defendants.
The project would include space for four new judgeships and would enable the court to provide basic services currently not possible due to space restrictions, such as a self-help center; appropriately sized public lobby and service counters; a properly sized and equipped jury assembly room and jury deliberation rooms, and rooms for family court mediation and attorney/client interviews, as well as a children's waiting room.
A site has not been selected for the new courthouse. To meet the planned building and parking requirements, a site of approximately 2.9 acres will be needed.
|
Architecture/Engineering Firm |
Skidmore, Owings & Merrill, LLP |
|
Construction Manager at Risk |
To be selected, schedule TBD |
|
Subcontractor Bidding |
Schedule TBD |
| Administrative Office of the Courts Judicial Branch Capital Program Office 455 Golden Gate Avenue, 8th Floor San Francisco, California 94102-3688 |
PHONE 415-865-4900 JBCP@jud.ca.gov |
FOR COURTS TO REPORT FACILITY ISSUES Customer Service Center: 888-225-3583 or csc@jud.ca.gov |