Start Date: July 12, 2011
Purpose: to provide ongoing oversight of the judicial branch capital construction program for trial and appellate courts throughout the state.
Feb 26, 203: Judicial Council delays 11 more courthouse projects absent additional funding
The council accepted the working group's recommendations to advocate for court construction funding restoration. If not, 11 more courthouse projects are delayed at least a year. News release | Judicial Council report | Listen (19 min)
Feb 8, 2013: Working Group recommends funding for all courthouse projects
The working group recommended that funding be requested of the Legislature so that all active courthouse projects could proceed in the upcoming fiscal year. Without funding restoration, 11 urgently needed projects will not be able to move forward as scheduled. News release
Jan 17, 2013: Judicial Council approves delay of four more court construction projects
Justice Brad Hill, Chair of the Court Facilities Working Group, presents the group's recommendations to delay courthouse projects in Sacramento, Fresno, Nevada City, and Los Angeles, pending the outcome of the state budget for fiscal year 2013-2014.
News release | Judicial Council report | Listen (10 min)
Dec 17, 2012: Invitation to comment
Working group draft recommendations resulting from the meeting Dec 13 posted for public comment.
Dec 13, 2012: More cuts possible to court construction program
With the potential for an additional shortfall to the courthouse construction budget, the Court Facilities Working Group will meet Thursday, Dec 13, to draft recommendations designating which of 23 courthouse projects should be indefinitely delayed. Meeting agenda
Oct 26, 2012: Judicial Council delays seven courthouse projects
The Judicial Council accepted the working group's recommendations to delay seven courthouse projects due to budget cuts. It also accepted the audit report from Pegasus-Global Holdings, Inc. and directed implementation of its recommendations. Judicial Council report
Sept 10, 2012: Recommendations from September 5-7 meeting
The working group recommended that seven court construction projects be indefinitely delayed due to budget cuts. It also accepted the audit report from Pegasus-Global Holdings, Inc. and endorsed implementation of its recommendations.
August 24, 2012: Audit subcommittee releases final audit report on court construction program
The audit subcommittee of the Court Facilities Working Group today released the final audit report on California’s court construction program.
July 23, 2012: Public comments on project reprioritization invited
The working group opened its five-week public comment process to gather information on which to base recommendations to the Judicial Council on which projects should proceed and which should be delayed.
July 13, 2012: Project reprioritization announced
Significant budget reductions will require that upwards of $500 million in court construction projects be delayed indefinitely. The working group announced an open, public process by which it will arrive at recommendations for the Judicial Council on which projects should proceed and which should be delayed.
April 24, 2012: Judicial Council meeting
The Judicial Council endorsed the Court Facilities Working Group's cost-cutting direction for court construction statewide, including the reassessment of 13 projects and further construction budget trimming on 24 projects.
Video report from the meeting
Video shown at the meeting: Courthouse conditions statewide
Audio from the meeting
Judicial Council report
In July, 2011 Chief Justice Tani Cantil-Sakauye named the members of a new Court Facilities Working Group, which will:
Members (as of October 1, 2012)
| Hon. Brad R. Hill, Chair Administrative Presiding Justice of the Court of Appeal, Fifth Appellate District |
Hon. Jamie A. Jacobs-May (Ret.) Retired Judge, Superior Court of California, County of Santa Clara |
| Hon. Patricia M. Lucas, Vice-Chair Judge of the Superior Court of California, County of Santa Clara |
Hon. Jeffrey W. Johnson Associate Justice of the Court of Appeal, Second Appellate District, Division One |
| Mr. Michael J. Bocchicchio, AIA Former Associate Vice-President, University of California System and Former State Architect of California |
Hon. Laura J. Masunaga Presiding Judge of the Superior Court of California, County of Siskiyou |
| Hon. Donald Cole Byrd Presiding Judge of the Superior Court of California, County of Glenn |
Mr. Stephen Nash Court Executive Officer Superior Court of California, County of San Bernardino |
| Mr. Anthony P. Capozzi Attorney at Law |
Hon. Gary R. Orozco Assistant Presiding Judge of the Superior Court of California, County of Fresno |
| Mr. Stephan Castellanos, FAIA Principal Architect Derivi Castellanos Architects Former State Architect of California |
Hon. David Edwin Power Judge of the Superior Court of California, County of Solano |
| Hon. Candace D. Cooper (Ret.) Retired Justice, Court of Appeal, Second Appellate District |
Ms. Linda Romero Soles Court Executive Officer Superior Court of California, County of Merced |
| Hon. Keith D. Davis Judge of the Superior Court of California, County of San Bernardino |
Mr. Larry Spikes County Administrative Officer County of Kings |
| Hon. Samuel K. Feng Judge of the Superior Court of California, County of San Francisco |
Mr. Kevin Stinson Assistant Clerk Administrator Court of Appeal, Fourth Appellate District, Division Three |
| Hon. Robert D. Foiles Assistant Presiding Judge of the Superior Court of California, County of San Mateo |
Mr. Val Toppenberg Consultant Former Redevelopment Director for City of West Sacramento and for City of Merced |
| Ms. Melissa Fowler-Bradley Court Executive Officer Superior Court of California, County of Shasta |
Hon. Robert J. Trentacosta Assistant Presiding Judge of the Superior Court of California, County of San Diego |
| Hon. William F. Highberger Judge of the Superior Court of California, County of Los Angeles |
Mr. Thomas J. Warwick, Jr. Attorney at Law |
For September 5–7, 2012, meeting
In preparation for this meeting, the working group requested comment on draft criteria to be used in determining which projects among 31 funded by Senate Bill 1407 should move forward and which may need to be indefinitely delayed, given reduced funding. The working group also invited written comments on the projects themseves.
Meeting binder: includes agenda, meeting reports and other materials
Written comments by court:
ARCHIVE
For October 19-20, 2011, meeting
In preparation for this meeting, the working group requested written input from the 34 courts slated to receive new or renovated courthouses under Senate Bill 1407. The courts’ submissions are below.
List of SB 1407 projects
Questions or comments about this working group may be emailed to capitalprograms@jud.ca.gov
Apr 26, 2013
Judicial Council Adopts New Budget Process for Trial Courts
Apr 19, 2013
Judicial Council to Consider New Budget Process for Trial Courts
Feb 26, 2013
Council Delays 11 More Court Construction Projects
Feb 19, 2013
Judicial Council To Consider More Court Construction Delays
Jan 17, 2013
Judicial Council Delays Four More Courthouse Projects
Dec 20, 2012
Budgets Reduced on Four Court Construction Projects
Dec 13, 2012
Four More Courthouse Projects May Be Delayed
Dec 6, 2012
More Cuts Possible to Court Construction Program
Nov 1, 2012
Budgets on Seven Courthouse Construction Projects Reduced
Oct 26, 2012
Judicial Council Delays Seven New Courthouses
September 10, 2012
Indefinite Delay for Seven Courthouse Construction Projects
September 7, 2012
Working Group Recommends Implementation of Audit
August 24, 2012
Audit of Court Construction Program Released
July 13, 2012
Further Cuts Ahead for Statewide Court Construction Program
May 4, 2012
Progress Report: Independent Oversight Consultant
Apr 24, 2012
Video: Judicial Council Accepts Recommendations of Court Facilities Working Group
Apr 16, 2012
Oversight Committee Recommends Reassessment of 13 Courthouse Projects for Cost Reductions
Jan 12, 2012
Independent Oversight Consultant Selected
Oct 24, 2011
Court Facilities Working Group Recommends Cost Reductions
Oct 3, 2011
Court Facilities Working Group Invites Public Comment on Courthouse Projects
Aug 30, 2011
Court Facilities Working Group Seeks Independent Expert
July 12, 2011
Chief Justice Names Court Facilities Working Group Members